Upgrading one workshop’s station: 64.2% output efficiency and a 25% saving
A single workshop is a good place to start a station upgrade. The boundary is small, the demand is well understood, and the result can be measured without disentangling the rest of the plant. One compressor manufacturer did exactly that in its own rotor-machining workshop, and the verification report — number 2023YS211, issued by a national testing institute — gives a clean set of numbers.
The three-week diagnosis
Rather than specifying equipment first, the team ran energy testing on the existing station for three weeks. What it found:
- Several machines running below full load, which drags down the efficiency of the whole set. A lightly loaded screw compressor has poor specific power, and the effect compounds when several units share the duty.
- High moisture content and poor air quality, which required treatment downstream.
- No metering, so the cost of air could not be attributed or tracked.
- No monitoring, so faults and maintenance intervals depended on someone noticing.
- Leakage in the distribution piping, which is the standard hidden loss in any plant that has never audited it.
Three of those five findings are not compressor faults at all. That is the usual ratio in a first station audit.
The rebuild
The new station used a two-stage screw compressor at 132 kW, with a heat-recovery system, zero-air-loss drainage on the receiver, a zero-air-loss refrigerated dryer, precision filtration and aluminium distribution piping. A control platform was added with a phone app for live data, prioritised machine selection, visualised status, automatic metering, remote monitoring, fault alarms and lifecycle tracking.
Two details in that list are easy to skip and hard to justify skipping later:
- Zero-air-loss drains. Every manual or timer drain dumps compressed air along with the condensate. On a station running continuously, that loss accumulates all year and appears nowhere in a maintenance budget.
- A dryer chosen for its performance at real ambient conditions, not for its nominal figure at rated inlet. The station’s own dew point has to hold in summer.
Heat recovery was included in the same project, which is the sensible sequence: the compressor room is already being rebuilt, and the recovery exchanger is a marginal cost at that point.
The measured result
| Parameter | Measured |
|—|—|
| Comprehensive output efficiency | 64.2% |
| Margin above the Grade-1 threshold | 6.2 percentage points |
| Energy saving against pre-retrofit | more than 25% |
| Annual electricity saved | more than 350,000 kWh |
| CO₂ avoided | about 350 t per year |
The workshop station was certified at Grade-1, and the process ran from preparation in February 2023 to the new station operating in May 2023 — roughly three months, of which the three-week measurement phase came first.
Why a workshop-scale project is worth doing first
There is an argument inside most plants about whether to rebuild the whole station or nothing. A workshop-scale project settles that argument with data:
- The measurement is clean. One workshop’s consumption is separable, so the before-and-after comparison does not depend on allocation assumptions.
- The disruption is bounded. Re-piping one workshop can be scheduled into a shutdown; re-piping the plant cannot.
- The findings repeat. Leakage, missing metering, poorly sequenced machines and air quality problems found in one workshop are usually present everywhere. The first project tells you what the second one will cost.
- The result is verifiable by a third party at a defined boundary, which is what a capital case needs.
What the two stations have in common
Read alongside the same manufacturer’s whole-plant station retrofit, the pattern is consistent: the biggest single gain came from the network, not the machine. Pressure loss, leakage and treatment inefficiency accounted for more than the compressor replacement did, and the compressor replacement was what made the station worth certifying.
That is the practical message for a plant considering a Grade-1 project. The certificate is earned by the whole station — and the parts of the station that are cheapest to fix are the ones that were never designed in the first place.
—
Industry practice note. Facts as reported by industry press; the station described is not a SIND project.
Planning a compressed-air upgrade? Talk to SIND’s engineers.
Facts as reported by industry press; the project described is not a SIND project.
Planning a compressed air project?
Talk to an engineerPublished November 16, 2026.