Rebuilding a station to Grade-1: a factory retrofit, start to measured result
The clearest case for what station-level grading rewards is a factory that rebuilt its own air station and published both the diagnosis and the result. The site is a compressor manufacturer’s main production base in Zhejiang; the retrofit ran from preparation in May 2023 to the new station running in September 2023, and was verified by a national testing institute under report number 2023YS494.
Because the plant belongs to a manufacturer, the diagnosis is unusually specific about what was wrong. That makes it useful as a checklist for any multi-decade station.
What the diagnosis found
Four findings, in order of how much energy they were costing:
1. Pressure loss in aged, undersized piping. In one workshop, the pressure drop between the supply main and the point of use reached 0.3 MPa. The workaround was to install extra receivers beside the machines that needed the pressure — which restores local capacity without restoring the header.
2. Wet, poor-quality air. Older compressors were delivering air with high water content, and the fix in use was additional desiccant dryers next to the equipment that needed dry air. That is treatment applied at the wrong end of the system, and it is expensive twice: once for the dryer, once for the pressure drop it adds.
3. No control system. Sequencing was manual, drains were manual, readings were taken by hand, and someone walked the room on a schedule to check machines.
4. Capacity that no longer matched demand. As workshops were expanded, machines were added, and the station grew without being redesigned.
What was built
- Four two-stage screw compressors at 132 kW, three duty and one standby, running at 8 bar.
- Zero-air-loss drainage on receivers and dryers, with automatic drains replacing manual ones.
- A zero-pressure-loss refrigerated dryer and a precision filter set, sized for the flow rather than inherited.
- Aluminium piping replacing the aged network, with the header route re-planned.
- A control platform with a wall-mounted visual display, sequencing the compressors and the treatment equipment together, with pressure, flow and dew-point data logged and analysed, and automatic start/stop around holidays.
The pipework scope is worth noting: more than 5,000 metres of new distribution piping. On a retrofit, the network is usually a larger share of the gain than the compressors, and a larger share of the disruption.
The measured result
After a period of operation, the station was tested:
| Parameter | Measured |
|—|—|
| Header pressure | 0.73 MPa |
| Pressure loss to the farthest terminal | below 0.01 MPa |
| Pressure dew point at 33 °C ambient | below 6 °C |
| Oil content | below 0.01 ppm |
| Filtration | below 0.01 µm |
| Comprehensive output efficiency | 61% |
| Margin above the Grade-1 threshold | 5.17 percentage points |
| Energy saving against pre-retrofit | more than 35% |
| Annual electricity saved | about 1.7 million kWh |
The pressure-loss number is the one to sit with. The station went from a 0.3 MPa loss in one workshop to under 0.01 MPa at the farthest terminal — a change that improves every machine on the network without touching any of them.
The order of work that produced it
The project team described its method in five commitments: personnel safety, meeting the air demand, engineering quality, construction efficiency, and cost control. Beneath those, the technical sequence is the one that matters and it is repeatable:
- Survey the whole plant’s air use, not just the compressor room.
- Design the station for the whole plant’s demand, including standby.
- Rebuild the network in the same project as the station, not after it.
- Instrument and control the station as one system, including treatment equipment.
- Verify after a period of operation, not at commissioning.
Step 5 is where most retrofits stop short. A station that is measured only on the day it opens is measured in its best condition.
What a plant can copy without the budget
The most transferable finding is the cheapest one: the extra receivers and desiccant dryers installed beside machines were symptoms of a network problem, not requirements. Plants often accumulate local fixes like these over years — a receiver here, a dryer there — and each one is evidence that the header is not doing its job. Finding and correcting the underlying pressure loss is usually the highest-return item in a station review, and it is frequently skipped because it looks like building work rather than energy work.
—
Industry practice note. Facts as reported by industry press; the station described is not a SIND project.
Planning a compressed-air upgrade? Talk to SIND’s engineers.
Facts as reported by industry press; the project described is not a SIND project.
Planning a compressed air project?
Talk to an engineerPublished November 16, 2026.