Station-level energy performance: what a compressed air station evaluation actually measures

A national standard for evaluating the energy performance of compressed air stations was launched in Shanghai on 13 March 2024 under the compressor standardisation committee, as part of the national carbon-peak and carbon-neutrality standards programme. The significance is structural: it formalises the move from grading machines to grading stations.

That move has a practical consequence for anyone buying or rebuilding a station. The certificate is issued for a system boundary, and the numbers behind it are produced by instruments most plants do not have.

The two figures that matter

Station evaluation rests on two measurements, and they are not the same thing.

Specific electricity consumption is the electricity consumed to deliver a unit volume of compressed air, referred to the compressor’s intake condition. It is a straightforward ratio: kWh in, cubic metres out, corrected to a stated reference state. Its weakness is that it says nothing about whether the cubic metres were useful.

Comprehensive output efficiency is the measure used for grading. It compares the useful compression work delivered — pressure and flow at the station outlet — with the electrical energy consumed by the whole station. Because it is built on delivered work rather than delivered volume, it captures pressure level as well as volume: a station delivering air at a higher pressure than the process needs scores worse, as it should.

The grading scheme used in the industry — the T/CGMA 033001 series, published in 2018 and in force since 2019 — sets three levels against this efficiency figure, with Grade 1 described as international advanced practice. The point of the new national standard is to give the same evaluation a national basis, aligned with the monitoring standard for compressor units and supply systems.

What has to be inside the boundary

A station evaluation covers everything between the intake and the delivery point:

  • All compressors, including the standby machine’s control behaviour.
  • Dryers and filters, whose pressure drop and regeneration energy are part of the station’s consumption.
  • Receivers and the main piping up to the delivery point, which determine how much pressure is lost before the air is used.
  • Cooling and ventilation of the plant room, where the heat rejection is significant.
  • The control system, since sequencing determines how many machines run and at what load.

That list is also the list of things a plant can improve without buying a compressor. Pressure loss and control are usually the cheapest points in a station evaluation and the ones most often neglected.

What it takes to be evaluated credibly

Four prerequisites, in order:

  1. A station-level electricity meter. Summing nameplate kW is not a measurement.
  2. Flow and pressure at the delivery point, logged, not read once.
  3. A defined and stable production period. Evaluation over a period when the plant is half-idle produces a figure that means nothing.
  4. Instrument calibration records. The evaluation is an engineering claim, and it will be checked.

Why plants should care before they are asked to

A station grade is increasingly used as evidence in energy-saving programmes, in procurement and in internal capital cases. But the operational value is more immediate than the certificate:

  • It puts the boundary around the right asset. A plant that measures only compressors will keep buying compressors to solve a piping problem.
  • It makes pressure loss visible as a cost. A 0.3 MPa drop between header and use point is an energy line item once the station is measured as a whole.
  • It forces the control question. Sequencing is where multi-machine stations lose the most energy with no component failing.

The sequencing of a station project

The industry’s own retrofit experience points to a consistent order of work, and it matches what the evaluation rewards:

  1. Measure the existing station — consumption, flow, pressure at several points, dew point.
  2. Fix the network — undersized mains, dead legs, leaks, filters that are never changed.
  3. Fix the control — sequence machines, set pressure to the process requirement rather than to the worst user.
  4. Only then change equipment — and size it against the demand that remains after steps 2 and 3.

Plants that start at step 4 pay for capacity they did not need to buy.

—

Industry standards note. Meeting details as reported by industry press; SIND is not involved in the drafting committee.

Planning a compressed-air upgrade? Talk to SIND’s engineers.

Facts as reported by industry press; the project described is not a SIND project.

Planning a compressed air project?

Talk to an engineer
SIND Applications Engineering

The SIND applications engineering team reviews compressed air duty points, sizes systems and writes the technical articles published on this site.

Published November 16, 2026.